Haishang Plaza is Under Construction

January 16th, 2017

Haishang Plaza Construction Site January 16, 2017

Haishang Plaza construction is well under way since breaking ground in April 2016.  Construction has since begun on the East and North Loft towers as well as the West SOHO tower.  Currently the East tower is up to the 9th floor, and the North and West towers are following slightly behind.  Due to intense smog conditions, the construction has been on and off causing months of delay.  The concrete frame is anticipated to be finished by May 2017 and the final completion of the Haishang Plaza is expected to be in May or June 2018.